top of page

Memorial Thicket℠ Memorial Drive Construction/Resurfacing

  • Jan 26
  • 1 min read

Memorial Drive Resurfacing


The City of Houston notified the Energy Corridor District that they have begun a maintenance project to resurface Memorial Dr. between SH 6 and Eldridge Pkwy. While it will be nice when the project is completed, it’s going to create traffic congestion during construction.  The City has put out traffic control measures and construction is in full swing.  The work did begin at SH 6 and will progress eastbound toward Eldridge. The estimated construction duration is 60 days. The preliminary schedule provided by the City of Houston is as follows:


CONSTRUCTION SCHEDULE

Weeks of 1/12 - 2/2          Mobilization; Mill and Level Up - Lanes 1-5

Weeks of 2/9 - 3/2            Install Glass Grid and Overlay - Lanes 1-5


Week of 3/9                      Clean Up; Restoration; Striping

Week of 3/16                    Demobilization


THANKS FOR BEING THE EYES AND EARS OF THE NEIGHBORHOOD.  SAFETY IS A GROUP EFFORT.


SAFETY FIRST!



bottom of page